An E-5 with dependents at Dyess now receives $1,872 a month in Basic Allowance for Housing. That rate expires December 31, 2026. The Defense Travel Management Office raised 2026 rates for the Abilene/Dyess housing area, known as TX270, by about 24% on average, effective May 16. The increases run from 18% to 28% depending on pay grade and dependency status. The notice says 2027 rates "will be announced later and may be different." If you're budgeting a lease or a purchase this fall, your largest housing input carries an end date and no confirmed replacement.

That end date is one sign of a timing problem in Abilene housing. Most coverage of Dyess growth focuses on the B-21 Raider. The personnel arriving in the next few years are tied mainly to the B-1 fleet, and they're arriving faster than the new housing approved for them can be built.

The temporary BAH rate

The temporary Abilene schedule says its calculations used housing data available as of April 2026, so even the corrected rate reflects the market as it stood in the spring. The Department of Defense acknowledged a gap large enough to fix mid-year, but the fix ends with the calendar year.

Local commentary shows why the rate lagged. In a September 4, 2026 KTAB report, Maj. Gen. John Nichols, vice president of the Military Affairs Council, said military housing accepts only BAH, which is "often lower than current rental rates in Abilene." He described "very low housing inventory that is moving extremely fast at elevated prices."

For a household reporting to Dyess in the next few months, the 2026 temporary rate and whatever 2027 brings may differ. A plan that only works at today's rate depends on a number the Pentagon hasn't set yet.

Three sources of demand, three different timelines

Abilene's housing demand is coming from several sources, and they don't move on the same schedule. The table sorts what the research supports.

Driver Stated scale Stated timing How firm
B-1 consolidation from South Dakota 44 total B-1s; about 3,000 additional airmen and family members "Next 3 years-ish" Nichols called these "rough estimates"
B-21 Raider beddown About 5,600 airmen and families, net, as a longer-range estimate 10 to 15 years Nichols said the figure was not exact; no Dyess arrival date published
AI data center development Cited by local Realtors as a demand driver Construction phase Some have questioned what happens after temporary construction workers leave

The B-1 row has the nearest deadline. At Hardin-Simmons University's "The Future Is Now" summit in September, Nichols said the Air Force decided to move the South Dakota B-1s "all here now in Abilene, Texas at Dyess."

The B-21 is real but further out. The Air Force calls Dyess the Raider's third Main Operating Base and plans more than 24 projects and $1.6 billion in infrastructure over the next decade. The groundwork has started. A $26.7 million fuels lab and refueler yard broke ground in December 2025 with completion expected by October 2027. The Mission Planning Facility, the first building exclusively for B-21 operations, was projected to break ground in 2026. Aircraft deliveries are expected to start at Ellsworth in 2027. The Air Force's February 2026 production announcement gave no Dyess date.

So the B-21 is a long program of construction and gradual growth. Over the next three years, the B-1 move is what changes how many households need a place to live.

Where new arrivals can live today

Dedicated military housing is limited. Nichols counted about 1,100 homes, with 710 on base and roughly 400 at Quail Hollow. Quail Hollow accepts non-military residents when there's room. With the neighborhood near capacity, he said officials are looking at contractual agreements that could move some longtime non-military residents out to make room for airmen. He called that "traumatic" for tenants who have paid rent faithfully for years. He also said airmen arriving on orders "cannot compete in this type of seller's market for a home."

Rentals off base were tight well before the fall. At the State of Abilene event in March 2026, rental broker Mike Powell reported fewer than 100 rentals available locally. His firm had 25 units listed and more than 200 applications. That's a count of available units and applications, not a vacancy rate, but it still means roughly eight applicants for every open door at one firm. On the purchase side, Ken Hogan, association executive of the Abilene Association of Realtors, told KTXS in June that some properties were drawing multiple offers "similar to how the kind of market we were in around during COVID."

Nichols also proposed an off-base development of 800 to 1,000 homes for military families. That was a suggestion at a public event, not an approved project.

New housing, sorted by how soon it could be ready

Abilene's supply is responding. Sorting the projects by stage shows how little can be ready within the B-1 window.

Closest to completion: single-family permits. The City of Abilene's second-quarter 2026 report lists 286 new single-family construction permits for April through June, up from 137 a year earlier. The same quarter recorded 19 multifamily permits. Permitted homes are the part of the pipeline most likely to reach buyers within a year or so.

Financed or announced: apartment communities.

  • The Lariat at Abilene has 312 units planned on 13 acres along McKinley Drive, funded by a $66 million HUD-backed construction loan to Martin Inderman Development.
  • Highland Meadows Apartments, a $28 million project at 2108 Scottish Road, appears in the city's Q2 report. The report gives no unit count or opening date.
  • Wayfare Communities announced a 272-unit community on 34.8 acres at 5457 Rebecca Lane, made up of 52 single-story buildings.

Earliest stage: rezoned land. On September 10, 2026, the Abilene City Council unanimously approved rezoning 166.9 acres at 6002 Texas Ave., near Dyess. The land is split into 117.91 acres of patio homes, 26.22 acres of multifamily and 22.77 acres of general retail. The council also approved 30.08 acres at 6648 Butterfield Trail for single-family homes. The applicant's agent said it would be developed with adjoining acreage as one subdivision. No builder has been named for either tract. Earlier in the spring, the council approved items making way for about 240 single-family lots, 800 multifamily units and 46 senior-living units.

A KTXS report quoted Hogan as saying "eventually it will help," and he said the impact won't be immediate. He estimated Abilene will need about 7,000 net housing units once Dyess growth settles. That's a local association's estimate, not an Air Force requirement. Even so, it's larger than everything listed above combined.

What the timing gap means if you're arriving on orders

Over roughly the next three years, several things are expected at once: up to 3,000 more people tied to the B-1 fleet, dedicated military housing near capacity, a small pool of rentals, and a BAH rate whose 2027 level is unknown. The new supply arrives in stages, with permitted homes first, then apartments, then rezoned land that still needs a builder, streets and utilities.

For a household with a report date, that leads to some practical steps:

  1. Budget at more than one BAH level. Check whether your rent or payment still works if 2027 rates come in below the temporary 2026 schedule. A lender or financial advisor can speak to your specific numbers.
  2. Start earlier than you would at a looser base. With more than 200 applications for 25 units at one firm in March, a short house-hunting window leaves little room.
  3. Ask about delivery dates, not approval dates. A rezoning vote or a financing announcement tells you land is being prepared. It doesn't tell you when anyone can move in.
  4. Include recently permitted single-family homes in your search. They're the part of the new supply most likely to be finished during the B-1 window.

FAQ

Is the B-21 why Abilene housing is tight right now? No source isolates the B-21's share. Local Realtors named the B-21 and the AI data center development as drivers. Nichols's September comments tie the near-term personnel increase to the B-1 consolidation.

Will the higher BAH continue into 2027? Unknown. The temporary rates expire December 31, 2026, and 2027 rates "will be announced later and may be different."

Who is building on the Texas Avenue land near Dyess? No developer or builder has been named. The council transcript lists only an agent for the property owner.

If you have orders to Dyess or are weighing a purchase before 2027 BAH rates come out, Elite Real Estate Group can help you compare what you can find today against what's actually on track to be finished. Our veteran agents work with VA buyers and relocating families on firm timelines. Contact Us to start planning around your report date.